The schedule for our Brookline renovation project has been updated with important dates and news.

End of March, 2003 - Loysen + Kreuthmeier issues drawings
Early April 2003 - Short List of General Contractors selected
Mid April - April 7 & April 8, 2003 - Minority and Women Business Owners' outreach sessions conducted
Mid April - First of May 2003 - Bidding Period
Mid May 2003 - Bid Review and award of General Contractor
Mid May 2003 - Library will temporarily close for renovations on May 20 at 7 p.m. End of May 2003 - Library hosts a Construction Kickoff for the community on May 31 at 10 a.m.
June 2003 - Construction begins (*)
December 2003 - Construction complete (*)
February 7, 2004 - Grand Re-Opening Celebration from 10 am to 2 pm.

(*) Approximate